Capacité atelier × charge
Capacité effective = capacité brute × OEE − temps de setup. OEE = Availability × Performance × Quality (norme TPM).
Capacité totale effective
148.3 h/j
Charge totale
156.9 h/j
Taux d'occupation global
105.8 %
OEE moyen
76.2 %
| Ressource | Type | Capacité brute | A × P × Q | Setup | Capacité effective | Charge | Occupation |
|---|---|---|---|---|---|---|---|
Laser fibre TruLaser 3030 MAC-LASER1 | machine | 16 h/j | 92 × 88 × 97 = 79% | 0.5 h | 12.1 h/j | 12.5 h/j | 104% |
Laser CO2 Bystronic MAC-LASER2 | machine | 16 h/j | 87 × 82 × 96 = 68% | 0.6 h | 10.4 h/j | 11.0 h/j | 106% |
Centre usinage CN DMG-MORI MAC-CN1 | machine | 16 h/j | 78 × 85 × 95 = 63% | 1.2 h | 8.9 h/j | 14.8 h/j | 167% |
Tour CN Mazak MAC-CN2 | machine | 16 h/j | 84 × 83 × 94 = 66% | 0.8 h | 9.7 h/j | 10.0 h/j | 103% |
Presse hydraulique 400T Schuler MAC-PRESSE | machine | 16 h/j | 80 × 78 × 93 = 58% | 1.5 h | 7.8 h/j | 13.5 h/j | 173% |
Robot soudure MIG ABB IRB-2600 MAC-SOUDR1 | machine | 16 h/j | 90 × 86 × 96 = 74% | 0.4 h | 11.5 h/j | 11.8 h/j | 103% |
Poste soudure TIG manuel MAC-SOUDR2 | machine | 8 h/j | 95 × 85 × 95 = 77% | 0.2 h | 5.9 h/j | 5.8 h/j | 98% |
Ligne assemblage modulaire LIGNE-ASS1 | machine | 16 h/j | 93 × 90 × 98 = 82% | 0.3 h | 12.8 h/j | 10.5 h/j | 82% |
Cabine peinture poudre + tunnel CAB-PEINT | machine | 16 h/j | 88 × 82 × 94 = 68% | 0.6 h | 10.3 h/j | 9.2 h/j | 90% |
Op. découpe (équipe matin) OP-DEC1 | operateur | 8 h/j | 95 × 92 × 99 = 87% | 0.0 h | 6.9 h/j | 6.5 h/j | 94% |
Op. découpe (équipe après-midi) OP-DEC2 | operateur | 8 h/j | 93 × 90 × 99 = 83% | 0.0 h | 6.6 h/j | 6.2 h/j | 94% |
Op. usinage CN (qualifié) OP-USI1 | operateur | 8 h/j | 94 × 95 × 99 = 88% | 0.0 h | 7.1 h/j | 7.8 h/j | 110% |
Op. emboutissage chef d'équipe OP-EMB1 | operateur | 8 h/j | 92 × 90 × 97 = 80% | 0.0 h | 6.4 h/j | 7.0 h/j | 109% |
Soudeur certifié EN 287 OP-SOU1 | operateur | 8 h/j | 94 × 92 × 99 = 86% | 0.0 h | 6.8 h/j | 6.5 h/j | 95% |
Soudeur TIG OP-SOU2 | operateur | 8 h/j | 90 × 88 × 97 = 77% | 0.0 h | 6.2 h/j | 5.5 h/j | 89% |
Op. assemblage senior OP-ASS1 | operateur | 8 h/j | 93 × 94 × 99 = 87% | 0.0 h | 6.9 h/j | 6.8 h/j | 98% |
Op. assemblage OP-ASS2 | operateur | 8 h/j | 91 × 88 × 97 = 78% | 0.0 h | 6.2 h/j | 6.0 h/j | 97% |
Op. peinture / finition OP-FIN1 | operateur | 8 h/j | 90 × 85 × 96 = 73% | 0.0 h | 5.9 h/j | 5.5 h/j | 94% |
Lib utilisée : lib/toc.ts — fonctions oee(), effectiveCapacity() et analyse().